Improving sanitation in floating communities along the Tonle Sap Lake in Cambodia. Preparing for/building in the floating village. August 16th - 18th, 2016. By: Joanne Wu
"Do you have this?" I ask acutely aware of the
language barrier between me and the grocery store representative as I point,
earnestly, to a picture of corn kernels on my phone.
He looks at my screen, furrows his eyebrows, and shakes his
head no.
We're in the middle of Aeon supermarket buying ingredients to
make a thank you treat for Hakley and his family, who will be hosting us during
our stay at the floating village. We were planning on making kettle corn but no
corn kernels means no kettle corn. Ok, that's fine. What's another no bake
treat that we can make? (We don't have an oven at the Airbnb that we're staying
at). I glance around and spot some corn flakes.
"Ah-ha! What about peanut buttery cornflake
clusters?" I propose. "We'll need peanut butter, corn syrup, and corn
flakes." I pace up and down the bakery aisle looking for corn syrup and
let out a little sigh: Aeon doesn't carry it. My mouth twists and I take a
second to think. Then, lightbulb: honey! (as a corn syrup substitute)
As I place the corn flakes, peanut butter, and honey on the
conveyer belt I muse on how this experience is illustrative of the type of
flexibility we'll need to demonstrate as we move forward with prototyping our
designs in Cambodia.
--
We leave Wednesday, August 17th at 8 am for the floating
villages. We'll be taking a 3 hour van ride to Chhnok Tru, where we'll then
take a 30 minute boat ride into the floating community of Phat Sanday. There
we'll be implementing two ideas to adapt the HandyPod system for use with
stilted houses along the lake: (1) a stand alone stilted support structure for
the HandyPod system and (2) a hand crank that will allow residents to reel in
and extend the corrugated tubing in the system.
We'll be at the lake Wednesday afternoon, Thursday, Friday,
and Saturday and leave Sunday morning. The plan is to buy materials on Wednesday
afternoon, construct the stand alone stilted support structure on Thursday, and
then build the hand crank on Friday and Saturday. With breaks every afternoon
for a siesta… you can't beat the afternoon heat here folks:
![]() |
| Sietsta Time |
Taking siestas wasn't the only instance when we modified our
plans to accommodate local conditions:
After dimensioning and CADing up a stilted support structure
for 6m high water levels, Hakley told us that historically the water level only
rises to ~3-4m. So we did some quick back of the envelope calculations to scale
our stilted support design down from a height of 6m to 3m. It felt strange
spending so much time entrenched in details in CAD only to leave the success of
the structure up to a few back of the envelope calculations but we built in
some buffer, crossed our fingers, and sent Yao off to procure some materials.
While Yao, Hakley, and Virak were out buying materials, Rachel
and I brainstormed how we were going to construct the support structure. “Does
it make more sense to construct this part or that part first..?” We made some
somewhat arbitrary decisions and drafted up a plan. Luckily Hakley and Virak
have quite a bit of experience installing these systems for various types of
houses along the lake. We were able to go over our construction plans with
them, discuss the pros and cons of certain choices, and refine the process so
that we were pre-fabricating parts of the structure in a way that enabled easy
transportation to the installation site.
--
My major take-away from day 1 of construction was this: plan,
plan, plan, but also plan to change your plans. All of the thought that goes
into planning is important and germane, but it’s also important to be receptive
to new information and suggestions.
Here are a few of my favorite photos from our first day of
construction:
![]() |
The gang. From left to right: Chandy, Rachel, Yao, Hakley, Virak
|
![]() |
| Constructing the stilted support |
![]() |
| Moving the stilted support the the boat for transport to the installation site |
![]() |
| Stilted support on the boat for transport |
With Hakley, Virak, and Chandy’s help we were able to finish
constructing the stilted support structure in one day. I’d say we were 90%
successful! To achieve that remaining 10% we’re planning on making two changes:
(1) modifying the dimensions so that the blue plastic containers are more
tightly constrained (less wiggling will likely equal less breakage) and (2)
optimizing the design so that it’s easier to build from the bottom up (vs. the
top down like we did at the lake).
The next two days of construction will be focused on the hand
crank. Until then, take care!
- Joanne